한국해양대학교

Detailed Information

Metadata Downloads

육상에서 제작되는 대형 해양구조물의 Pre-Service 해석 및 설계에 대한 연구

DC Field Value Language
dc.contributor.author 이상길 -
dc.date.accessioned 2017-02-22T06:51:18Z -
dc.date.available 2017-02-22T06:51:18Z -
dc.date.issued 2014 -
dc.date.submitted 57042-05-01 -
dc.identifier.uri http://kmou.dcollection.net/jsp/common/DcLoOrgPer.jsp?sItemId=000002175658 ko_KR
dc.identifier.uri http://repository.kmou.ac.kr/handle/2014.oak/9916 -
dc.description.abstract The demand of floating type offshore structures has been being increased since the last several decades in offshore construction field. Generally, the fabrication and assembly of floating offshore structures have been carried out in the dry dock of the shipyard by stacking unit blocks sequentially from lower to upper levels. However the use of dry dock facilities has great dependency on deck schedule and tight fabrication process of yard. So it is difficult to incorporate any design change or modification required by client. For that reason, the on-ground fabrication methodology was used for several offshore floating structures to reduce total construction schedule and have flexibility in fabrication phase since hull and topside part can be fabricated at the same time. As of now the on-ground built is not an option for construction of large offshore floating structure. Nonetheless, the guide lines for on-ground fabrication methodology have not been established. Therefore this paper discusses the optimum design, structural validation and practical operation method for Superlifting system and Loadout System based on successfully performed GK-FPS (41,060mt dry weight GUMUSUT KAKAP Semi FPS) project in April 2012 and April 2013 respectively. The major characteristics of Superlifting technology, which depend on configuration of the object to be lifted, were its heavy weight(22,531mt), high lifting height(45.5m) and big size(90m*90m) based on GK-FPS project. So special consideration should be required for safe Superlifting operation since its scale is remarkable compared with previous cases of other offshore structures. The Superlifting technology is very comprehensive, challenging and perilous work. for that reason, the first, the ground foundation should be verified and monitored during Superlifting operation as well as its settlement should be considered for structural integrity check of Superlifting Structure. The second, a lot of hinge connections such as knife edge bearing (KEB) and tension plate should be inevitable for optimum design even though these designs are very complicated and have inherent risk. The third, pre-load test for structural validation of Superlifting structure should be done by using topside weight, which is required to check the topside integrity. The last, the topside modules should have enough strength to have the practicable twist value during going up to target lifting height since the lifting point might be controlled by strand jacks independently. Loadout operation looks like easier work compared with Superlifting operation. but it is misjudgment in case of skidding heavy weight structure. For the effective Loadout operation, the concept design should be preceded with regard to the pulling force flow considering the stability of quay and capacity of vessel. Generally, the fixed anchor is located on the vessel and specified fenders is between vessel and quay to transfer pulling force to quay, which sometimes causes many reinforcement of quay and vessel for skidding heavy structure. In order to solve this problem, the new concept was developed and presented based on viewpoints of costwise in this paper, which is named as“Direct Connection Method” since pulling force flows only skidbeam connection to offset pulling force by itself. Foresaid developed methodologies for Superlifting and Loadout operation have been verified through successfully accomplished GK-FPS project done at MMHE (Malaysia Marine and Heavy Engineering) yard, which broke the world record. Therefore, this paper describes the developed effective method and enhanced engineering technology for Superlifting and Loadout Operation to be going to be guidelines of efficient on-ground fabrication of heavy structure in offshore field for the future application. -
dc.description.tableofcontents List of Tables iv List of Figures ix Abstract xiii 제 1 장 서 론 1 1.1 연구배경 1 1.2 GK-FPS 육상제작 2 1.3 기존연구 6 1.3.1 수퍼리프팅 방법 6 1.3.2 선적방법 14 1.4 연구방향 19 1.4.1 기존방법과의 차이점 19 1.4.2 단순화된 캣헤드의 힌지 설계기법 개발 21 1.4.3 선적공법 개발 22 제 2 장 대형해양구조물 육상제작 기법 24 2.1 상부구조물 수퍼리프팅을 위한 구조물 24 2.2 수퍼리프팅 설계 기법 27 2.3 대형해양구조물 선적을 위한 구조물 39 2.4 선적설계 기법 43 제 3 장 인장력을 받는 힌지에 대한 연구 52 3.1 캣헤드의 인장판 52 3.2 인장판의 설계 기법 53 3.3 인장판 해석방법 수립 90 제 4 장 압축력을 받는 힌지에 대한 연구 93 4.1 KEB 93 4.1.1 KEB 설치위치 93 4.1.2 KEB의 형상 94 4.1.3 KEB의 설계 개념 95 4.2 KEB의 설계기법 95 4.2.1 KEB의 설계순서 95 4.2.2 KEB의 두께 결정 97 4.3 KEB의 설계 103 제 5 장 선적방법에 대한 연구 107 5.1 Strand Jack을 사용하는 선적방법 107 5.2 기존 선적방법과 직접연결방법의 설계개념 108 5.3 기존 선적방법과 직접연결방법의 장단점 110 5.4 기존 선적방법을 위한 선적 구조물설계 114 5.5 직접연결방법을 위한 선적 구조물설계 119 5.6 직접연결공법 적용 138 제 6 장 결론 140 감사의 글 143 참고문헌 144 부록 A Dynamic Characteristics of Superlifting Structure 146 부록 B Flow Chart for Wind Spectral Analysis 155 부록 C Collapse Analysis for Jacking Leg 156 부록 D Overhang Length Check 162 부록 E Mooring Arrangement for GK-FPS 170 부록 F Preload Test Analysis 174 부록 G Twist Analysis 178 부록 H GK-FPS Picture 182 -
dc.language kor -
dc.publisher 한국해양대학교 -
dc.title 육상에서 제작되는 대형 해양구조물의 Pre-Service 해석 및 설계에 대한 연구 -
dc.title.alternative A Study on Pre-Service Engineering for Large Offshore Structure to be built on Ground -
dc.type Thesis -
dc.date.awarded 2014-02 -
dc.contributor.alternativeName Lee Sang-Gil -
Appears in Collections:
조선해양시스템공학과 > Thesis
Files in This Item:
000002175658.pdf Download

Items in Repository are protected by copyright, with all rights reserved, unless otherwise indicated.

Browse